June 2025

PROGRESS OF WORKS

Danube Pearls 1 and 2 are getting windows and facade doors. At Danube Pearl 3, the installation of the ground floor walls has been completed. Danube Villa 3 is the first villa to receive the floor slab between the ground floor and the upper floor.

May 2025

PROGRESS OF WORKS

In the previous period, we completed the foundation footings of the ground floor, foundation walls, compacted soil, compacted gravel, the lean reinforced concrete slab, the structural reinforced concrete slab on the ground, and the waterproofing of the foundation walls. We also assembled the ground floor walls next to the previously installed basement walls. In this way, we completed the ground floors of Dunavske Vile 1, 2, and 3, as well as Dunavski Biser 3. Villa 4 is quickly catching up with the other buildings. In June, we will show you the view from the upper floor of all these buildings. You will be able to imagine the view from the floor overlooking the Danube, the windmills in Banat, Belgrade and Avala, and Fruška Gora.

March 2025

PROGRESS OF WORKS

The thermal insulation of the basement is being completed. The structures of Dunavski Biser 1 and 2 are structurally finished, with only the façade and exterior joinery remaining. The assembly of Dunavske Vile 2, 3, and 4, as well as Dunavski Biser 3, has begun. The horizontal distribution of installations for Dunavski Venac has been completed, and the floor slab has been poured. The production of exterior joinery has also started. All 15 buildings will be structurally completed and enclosed with exterior joinery and security entrance doors by the end of July.

January 2025

PROGRESS OF WORKS

We have installed staircases, providing our customers with access to the rooftop. Visit us and enjoy the panoramic view of the Danube, Srem, Bačka, and Avala.

December 2024

PROGRESS OF WORKS

Biser 1 has received the final slab and access to the flat roof. Biser 2 has reached the second floor, and the roof slab is expected soon. The villas are ready for the installation of ground floor walls. The cornice is also being prepared for the installation of the ground floor. Weather conditions no longer pose a challenge. The planned completion of prefabricated construction work is set for the end of spring.

November 2024

PROGRESS OF WORKS

We are continuing with the installation of walls, ground floors, and upper floors. We have started waterproofing the basement walls. Stay tuned!

October 2024

PROGRESS OF WORKS

We are continuing with the installation of walls, ground floors, and upper floors. Stay tuned!

September 2024

PROGRESS OF WORKS

We are continuing with the installation of walls, ground floors, and upper floors. Stay tuned!

August 2024

PROGRESS OF WORKS

The construction of the basement and foundations has been completed. The installation of walls, ground floors, and upper floors has begun. Stay tuned!

June 2024

PROGRESS OF WORKS

The completion of the basement and foundation construction. By the end of the month, the installation of walls, ground floors, and upper floors will begin. Stay tuned!

March 2024

PROGRESS OF WORKS

The basements have been built, and the reinforcement for the foundations of all the structures is ready.

February 2024

PREPARATION WORKS

We continue preparatory work on the future location of the Danube heights settlement.

December 2023

PREPARATION WORKS

We continue preparatory work on the future location of the Danube heights settlement.

November 2023

PREPARATION WORKS

We continue preparatory work on the future location of the Danube heights settlement.

October 2023

PREPARATION WORKS

We have started preparatory work on the future location of the Danube heights settlement.